Shutdown

  1. Close the shut-off valve in the inlet pipe.
  2. Switch the switchgear to standby mode.
  3. Drain the pump chamber.
    Activate the pump in manual mode and drain the pump chamber.
  4. Close the shut-off valve in the discharge pipe.
  5. Pump out the leftover fluid through emergency draining.
  6. Switch off the pumping station:
  7. Pumping station without a switchgear: Pull the plug out of the socket.
  8. Pumping station with a switchgear: Switch off the switchgear at the main switch.
  9. NOTICE! Prevent the pumping station from non-approved reactivation.
  1. The pumping station is decommissioned.

If the pump chamber is out of operation for a long time, do a “test run” at regular intervals (quarterly).