Operation

The pumping station operates in automatic mode by default and is switched on and off using the integrated level control device.

  1. Commissioning is done.
  2. Test run is done successfully.
  3. The operation and functioning of the pumping station are known.
  4. The discharge pipe is fully filled with water.
  1. Activate the pumping station:
  2. Pumping station without a switchgear: Put the plug into the socket.
  3. Pumping station with a switchgear: Activate the switchgear at the main switch. Set the automatic mode.
  4. Open the shut-off valve in the inlet and discharge pipe.
  1. The pump chamber operates in automatic mode and the pump is controlled depending on the water level.