Test run
Do a test run before putting the pump chamber into operation. A test run examines the correct functioning of the pump chamber. If necessary, adjust the switching points and the follow-up time of the pump.
- Pump chamber is installed correctly.
- Remove the pump chamber cover.
- Activate the pumping station:
- Pumping station without a switchgear: Put the plug into the socket.
- Pumping station with a switchgear: Activate the switchgear at the main switch. Set automatic mode.
- Open the shut-off valve in the discharge line.
- Fill the pump chamber with water through the chamber opening.
- Pump is switched on and off using the level control.
- Do no less than two full pumping procedures of all pumps for a test run.
- For two-pump chamber: The pumps must run in alternation, with one pump running for each pumping operation.
- Fill the discharge pipe fully with water to examine the duty point. Do more test runs until the discharge pipe is fully filled.
- Fit the chamber cover and prevent it from non-approved opening.
- The test run is completed.
- If the pump chamber is put into operation: Keep shut-off valve open in the discharge pipe.
- When the pump chamber is in standby mode: Close the shut-off valve in the discharge pipe.