Installing the pump chamber extension when using the D400 pump chamber cover

NOTICE

notice

Using a load distribution plate, a fully sealed pump chamber is not possible.

With a high ground water level and a load distribution plate, increased water ingress into the pump chamber is possible. This water ingress can overload the pump. There is a risk of pump system malfunction.

NOTICE

notice

If a D400 pump chamber cover is used, install a load distribution plate.

  1. Cut the pump chamber cover flange at the pump chamber or at the pump chamber extension.
  2. The load distribution plate must be provided by the customer.

1

Cover flange

When using the D400 pump chamber cover, a maximum pump chamber extension of 570 mm is possible. The load distribution plate adds 300 mm to the extension. Keep this in mind during installation. NOTICE! The load distribution plate must be provided by the customer.

If an extension higher than this minimum 300 mm is required, it is recommended to use standard concrete adjusting rings.

To install the load distribution plate correctly, make sure to cut off the cover flange on the pump chamber.

To meet road traffic requirements, make sure to install a dedicated substructure when filling the pit.CAUTION! The load distribution plate can be put on the pump chamber, but must be fully put on the dedicated substructure.

For more details, refer to the “Filling the pit” section.

Removing the cover flange
Removing the cover flange