Preparing pipe connections

Install and lay all pipes so that they are stress-free.

  1. Cut out the selected connection ports for the inlet and venting pipe and remove burrs.
  2. Lay the pipes with a downward slope to the pump chamber. Connect the pipes to the open connection ports using a KG sleeve and lubricants. NOTICE! To simplify the laying of electrical connection cables for the pump and level control device, use pipe bends in the on-site ventilation line. The maximum angle of the pipe bend is 30°. Also install a tie rod.
  3. Connect the on-site discharge pipe to the discharge port using clamp bolting. Make sure that the routing is frost-proof.
  4. Obey the applicable regulations to do a leak test.
  1. Pipe connections are prepared. Next step: Installing the pump chamber extension
Pipe connection preparation
Pipe connection preparation