Installing the pump chamber
1 | Pump chamber cover | X | Required pit depth |
2 | Pump chamber extension | Y | Pump chamber cover height |
3 | Pump chamber | Z | Max. pump chamber diameter |
4 | Venting/cable duct | ||
5 | Connection port DN/OD 150 | ||
6 | Connection port DN/OD 200 | ||
7 | Levelling layer | ||
8 | Underlay |
- Installation preparation is completed.
- The pit is excavated.
- The pump chamber cover is prepared.
- Installation location is prepared according to the consulting documents.
- Examine the floor of the pit for its bearing capacity.
- Install the load-bearing mineral mixture underlay and seal it.
- Add a levelling layer of sand and level it off.
- Prepare the on-site inlet, ventilation and discharge pipes.
- Install the pump chamber in the pit, align the connections with the on-site piping and drive them in evenly.
- Taking the surrounding surface level as a reference, examine and adjust these if necessary: the plumb-vertical alignment and position of the pump chamber, including the height of the pump chamber cover and pump chamber extension.
- The pump chamber is installed. Next step: Setting up the pipe connections.