Preparing the installation
General requirements
- Examine transport damage.
- Remove the transportation lock.
- Examine the scope of delivery.
- Examine that all components are in correct working condition.
- Put accessories aside and keep them for later use.
- Prepare the installation location:
- Install only outside of buildings.
- Do not install next to living and sleeping areas
- Do not install in peaty soils
- Keep in mind the maximum height adjustment.
- Prepare the pump chamber cover.
- Must be ordered separately.
- Obey EN 124 for the pump chamber cover class: A15, B125 or D400.
- Install a load distribution plate for pump chamber cover D 400:
Requirements for the cable connection to the switch cabinet
1 | Pump chamber |
2 | Switch cabinet |
3 | Cable pipe |
4 | Ventilation pipe |
- To control the pump system in view, e.g. manual pumping, control of the switching points, put the switch cabinet with controller next to the pit.
- Connect the switch cabinet and the pump chamber with a cable pipe of max. 5 m.
- Connect the cable pipe to the ventilation/cable ducts of the pump chamber.
- Lay the connection cable through the cable pipe.