Installing the lifting unit
1 | Slinging point |
2 | Fastening grooves for floor anchoring |
3 | Pump support bracket |
4 | Screw |
5 | L-bracket |
6 | Anchor bolt |
Install the lifting unit. Prevent the lifting unit from buoyancy and twisting. Anchor the lifting unit to the floor.
- Installation preparing work is done.
- Installation location is prepared as shown in the consulting documents.
- Applicable fixation materials are prepared.
- Put the lifting unit at the installation location and align it to the pipework.
- For the lifting unit supplied with pump support brackets, loosen the screws on the upper L-brackets.
- Adjust the faces of the pump support brackets with the floor. Hand tighten the screws on the support brackets.
- Mark the drilling holes for the fastening grooves. Mark the drilling holes for the fastening points of the pump support brackets.
- Put the lifting unit aside.
- Drill the holes according to the fixation materials used and clean the holes.
- Put the lifting unit back.
- Anchor the lifting unit to the floor with the fixation materials.
- Attach the pump support brackets to the floor with the bounded anchors.
- Tighten all screws.
- Lay the connection cable. Obey applicable regulations.
- The lifting unit is installed. Next step: Connecting the discharge pipe.