Shutdown

  1. Close the shut-off valve in the inlet pipe.
  2. Switch the switchgear to standby mode.
  3. Drain the collection tank.
    Activate the lifting unit in manual mode and drain the collection tank.
  4. Close the shut-off valve in the discharge pipe.
  5. Switch off the lifting unit.
    Pull the plug out of the socket. CAUTION! Prevent the lifting unit from not approved reactivation.
  1. The lifting unit is now decommissioned.

If the lifting unit is decommissioned for an extended time, do a functional check at regular intervals (quarterly). CAUTION! Do the functional check as described in “Test run”.