Connecting the ventilation pipe

The connection of a ventilation pipe is mandatory. Furthermore, ventilation is necessary to make sure that the lifting unit functions correctly. Follow these points to connect the ventilation pipe:

  • For floor-mounted or concealed-wall installation in buildings, route the ventilation pipe over the roof of the building.
  • For concealed-floor installation (underground installation) outside buildings, route the ventilation pipe over the surface.
  • Make sure that all connections are fully tight.

1

Ventilation connection

2

Discharge port

  1. Lifting unit is installed.
  2. Ventilation pipe is laid.
  1. Put the HT double socket on the open ventilation connection.
  2. Put the ventilation pipe into the HT double socket.
  1. Ventilation pipe is installed. Next step: Connecting a diaphragm hand pump to the drain connection (when it is necessary for emergency drainage).
Collection tank ventilation connection
Collection tank ventilation connection