Installing the lifting unit

1

Fastening grooves for floor anchoring

Install the lifting unit. Prevent the lifting unit from buoyancy and twisting. Anchor the lifting unit to the floor.

  1. Installation preparing work is done.
  2. Installation location is prepared as shown in the consulting documents.
  3. Applicable fixation material is given for the building floor. NOTICE! Follow the information on the fixation material.
  1. Put the lifting unit at the installation location and align it to the pipework. CAUTION! To prevent the switchgear from falling down, attach the switchgear to the lifting unit. The switchgear can break if dropped. NOTICE! Lifting unit must be upright.
  2. Mark the drilling holes of the fastening grooves.
  3. Put the lifting unit aside.
  4. Drill and clean the holes. Put into the dowels.
  5. Lay and align the noise insulation mat.
  6. Put and align the lifting unit to the noise insulation mat.
  7. Put into the fastening screws and washers through the fastening grooves. Put the fastening screws into the dowels.
  8. Fasten the lifting unit to the floor.
  9. To prevent the switchgear from flooding, fasten the switchgear to the wall at a sufficient height (see switchgear instructions).
  10. Lay the connection cable. Obey applicable regulations.
  1. Lifting unit is installed. Next step: Connecting the discharge pipe.
Lifting unit top view
Lifting unit top view