Installing the lifting unit
1 | Fastening grooves for floor anchoring |
Install the lifting unit. Prevent the lifting unit from buoyancy and twisting. Anchor the lifting unit to the floor.
- Installation preparing work is done.
- Installation location is prepared as shown in the consulting documents.
- Applicable fixation material is given for the building floor.
- Put the lifting unit at the installation location and align it to the pipework.
- Mark the drilling holes of the fastening grooves.
- Put the lifting unit aside.
- Drill and clean the holes. Put into the dowels.
- Lay and align the noise insulation mat.
- Put and align the lifting unit to the noise insulation mat.
- Put into the fastening screws and washers through the fastening grooves. Put the fastening screws into the dowels.
- Fasten the lifting unit to the floor.
- To prevent the switchgear from flooding, fasten the switchgear to the wall at a sufficient height (see switchgear instructions).
- Lay the connection cable. Obey applicable regulations.
- Lifting unit is installed. Next step: Connecting the discharge pipe.