Preparing the installation
- Unpack the lifting unit.
- Remove the transportation lock.
- Examine the scope of delivery.
- Examine that all components are in correct working condition. CAUTION! Do not install defective components. Defective components can lead to system failures.
- Put accessories aside and keep them for subsequent use.
- Prepare the installation location:
- Horizontal and flat installation surface
- Free space of min. 60 cm (2 ft) around the unit
- Feasible fixation with dowels
- Clean, free of coarse solids
- Dry
- Frost free
- Sufficiently lit
- For concealed-wall installation, follow these points:
- Inspection opening
- Minimum distance between wall and the unit: 20 mm
- Sufficient and regular air change for motor cooling CAUTION! Not sufficient air change can lead to overheating of the motor and a possible decrease of function of the lifting unit.
- Ventilation of the lifting unit over the roof
- Sufficient space for maintenance and repair: safe and easy access to tank opening, non-return valve, motor, and switchgear
- For concealed-floor installation, follow these points:
- Sufficient space for maintenance and repair: safe and easy access to tank opening, non-return valve and motor
- Ventilation of the lifting unit over the surface
- Outdoor switch cabinet for installation of the switchgear