Transportable wet installation

1

Pressure hose

2

Hose nozzle (included at Initial DRAIN)

3

90° elbow (pre-mounted)

4

Float switch

ON

Switching point: pump on

OFF

Switching point: pump off

OFF2

Pump off at deep suction in manual mode

Obey these points for installation:

  • Make sure that the pump cannot fall over.
  • Make sure that the pressure hose is securely fitted to the hose nozzle.
  • When submerging the pump, prevent air bubbles which can cause pumping problems. When placing the pump in a filled pit, submerge it at a small angle.
  • To prevent the pump from sinking into soft ground, use a hard surface at the site.
Transportable wet installation
Transportable wet installation
  1. Hose nozzle: Rp 1½" external thread with 30 mm (1.2 in) hose connection (included at Initial DRAIN).
  2. Pressure hose: minimum internal diameter 33 mm (1.3 in)
  3. Pipe clamp (diameter: 25 to 50 mm/1 to 2 in) for fastening the pressure hose at the hose nozzle.
  1. Screw the hose nozzle (included at Initial DRAIN) fully into the discharge port.
  2. Put the pipe clamp over the pressure hose.
  3. Put the pressure hose on the hose nozzle.
  4. Fasten the pressure hose to the hose nozzle with the pipe clamp.
  5. Set up the pump on site.
  6. Fasten the pressure hose in an applicable location (e.g. drain).
  1. The pump is installed.