Backfill the pit
Observe the following points when backfilling the pit:
- Backfill the pit according to local specifications and guidelines!
- Make sure that the pump chamber is in a consistent and vertical position.
- Secure pump chamber against buoyancy. If necessary, fill the pump chamber with water.
- The details of the filling material are minimum requirements. Observe local guidelines.
- Carry out backfilling and compaction on the piping in accordance with local specifications and guidelines.
1 | Underlay |
2 | Levelling layer |
3 | Compression layers |
4 | Substructure to the surface level |
5 | Chamber cover |
- The pit is backfilled up to the inlet areas at the chamber.
- Pump chamber is vertical.
- All pipe adaptors are connected and sealed.
- Pump chamber extension installed if necessary.
- Filling material for backfilling: Sand/gravel, without sharp-edged components, non-cohesive, grain size 0 ... 32 mm)
- Professionally backfill the pit and in layers at the same height up to the chamber neck. Comply with local regulations! Compress the individual layers properly (Dpr. 97 %).
- Restore surface level with a substructure according to local regulations.
- The pit is backfilled.
- Next step: Install the chamber cover.