Dig a pit and install pump chamber

NOTICE

notice

Ground installation (sub-surface installation): Comply with local regulations!

Civil engineering works are subject to strict local specifications. Observe the following points:

  1. Work may only be carried out by a trained specialist in underground and pipeline construction!
  2. Dig, prepare and backfill the pit
  3. Buoyancy safeguards
  4. Connection of plastic pipes
  5. Observe local regulations for earthworks!
  6. Slope angle
  7. Pit lining ...
  8. Consider frost depths!

Install pump chamber so that it is anti-buoyant and does not twist. Dig out the pit, taking the following points into account:

  1. Preparatory tasks completed.
  2. Pit dimensions specified.
  3. Groundwater lowering system installed.
  4. Filling material for underlay: load-bearing mineral mixture
  5. Filling material for levelling layer and for backfilling: Sand/gravel, without sharp-edged components, non-cohesive, grain size 0 ... 32 mm)
  1. Dig a pit.
  2. Professionally place and compact the underlay according to local specifications (Dpr 97 %).
  3. Professionally place the levelling layer according to the local specifications and level it.
  4. Insert the pump chamber into the pit.
  5. Align the pump chamber with the on-site piping.
  6. Vibrate the pump chamber evenly into the levelling layer.
    NOTICE! Vibrate the chamber base and base ribs completely into the levelling layer!
  7. Check the position of the pump chamber and correct if necessary:
  8. Pump chamber should be vertical!
  9. Chamber cover flat to surface level!
  10. To fix the pump chamber, professionally backfill the pit in layers up to below the inlet areas. Comply with local regulations! Compress the individual layers properly (Dpr. 97 %).
  11. NOTICE! Backfill and compact by hand at the pump chamber (blade, hand rammer)!
  1. Pump chamber installed.
  2. Next step: Lay, prepare and connect on-site pipework to the pump chamber.